Weekly Roadwork Report

 

TxDOT Paris District
For Nov. 4-10, 2018

Delta, Lamar and Red River

These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues. Motorists are advised to remain alert and pay particular attention to all signs, barricades and traffic controls, and reduce their speed as they approach and travel through work zones. They should also avoid distractions such as cell phones, eating, drinking, or car audio or navigation systems.

Various roadways throughout Delta, Lamar, and Red River counties will have crack seal work continuing this week. This work will require lane closures.

FM 197, Lamar County: Watch for temporary lane closures as workers widen and reconstruct existing pavement and upgrade drainage structures.

Delta, Lamar and Red River

From Loop 286 in Paris southeastward to SH 37. Watch for temporary lane and/or shoulder closures as work continues throughout this project.

US 271 safety upgrades, Red River County:
From FM 410 to the Red River-Titus County line. Watch for temporary lane and shoulder closures as workers upgrade metal guard fence and bridge rails, and extend and safety-treat drainage structures.

SH 37 safety upgrades, Red River County
From the Texas-Oklahoma state line south to the Red River-Franklin County line. Watch for work zones as workers upgrade metal-beam guard fence, replace or extend new structures and install safety end treatments.

FM 2648 widening, Lamar County: Watch for temporary, one-lane daytime closures as workers widen and rehabilitate the roadway, and safety treats cross drainage structures.

SH 24 expansion, Delta County: from Cooper, Texas, southwestward towards Commerce.
Watch for work zones and drive safely through construction areas while this roadway is being widened and improved. Drivers can expect lane closure shifts at various locations along the southbound lanes during the day. The outside southbound lane will be open to traffic each evening.

Lamar County

Work is scheduled to begin Nov. 5 to repair the slope at the southwest quadrant of the FM 79 overpass. This work will require the closure of the outside eastbound lane and should take approximately three weeks to complete, weather permitting.

Franklin and Hopkins Counties

These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues. Motorists are advised to remain alert and pay particular attention to all signs, barricades and traffic controls, and reduce their speed as they approach and travel through work zones. They should also avoid distractions such as cell phones, eating, drinking, or car audio or navigation systems.

SH 37, Franklin County: From Mt Vernon to Winnsboro. Watch for lane closures, and short traffic delays as crews prepare for surface operations. Flaggers will direct traffic.

SH 11, Hopkins County: From Winnsboro to Como. Watch for lane closures and short traffic delays as crews perform surfacing operations. Flaggers will direct traffic.

TxDOT Atlanta District
For Nov. 4-10, 2018

Bowie County
US 259 – At Red River north of De Kalb, constructing a new bridge.
US 67 – At Bassett Creek, upgrading guardrail on the bridge. Alternating one-way traffic across bridge controlled by signal lights.
US 67 – From FM 989 to FM 2148 North, resurfacing highway.

Cass County
FM 3129 – From US 59 to SH 77, upgrading guardrails and adding safety features to drainage structures.

Harrison County
Loop 281– at I-20 overpass, conducting preventative maintenance work on the bridge.
SH 43 – at I-20 overpass, conducting preventative maintenance work on the bridge.

Morris County
US 259 – From I-30 to FM 557, upgrading guardrails, repairing pavement and resurfacing highway.

Panola County
SH 149 – At SH 315, constructing overpass and widening the highway. SH 315 east of the intersection is back open.
US 59 – From Harrison County Line to FM 2792, upgrading guardrails, repairing pavement and resurfacing highway.
FM 699 – At FM 2517, reconstructing intersection. FM 699 closed to traffic on the north side of the intersection. The detour route is signed.

Titus County
US 271 – From the end of freeway section of US 271 to 0.3 mile south of FM 3417, extending freeway lanes and constructing an overpass at FM 3417.
US 271 – At Ripley Creek and Ripley Creek Relief, replacing bridges.

Upshur County
US 271– From SH 155 South to FM 726, upgrading guardrails, repairing pavement and resurfacing highway.