Weekly Roadwork Report

TxDOT Atlanta District

Feb 27 – Mar 5, 2022

 Bowie County 

  • I-30 – From FM 989 to AR State Line, reconstructing and widening highway, daytime work in the median. Motorists should watch for trucks and equipment pulling onto the interstate.
  • SH 8 – At Sulphur River, replacing bridges
  • SH 98 – At Anderson Creek, bridge replacement, with traffic restricted to one lane with signal lights controlling traffic through the work zone.

 Camp County 

  • SL 255 – From FM 1520 to US 271, constructing a highway, with County Road 2120 detoured

 Cass County 

  • SH 8 – At Sulphur River, replacing bridges
  • US 67 – Widening bridge at Jennings Slough. Signal lights controlling one-way traffic

 Harrison County 

  • I-20 – At US 59 overpass, replacing the bridge, with US 59 traffic shifted to southbound lanes.
  • I-20 – At Lansing Switch Road, constructing a new bridge over the interstate. Lansing Switch Road is closed to traffic. Possible lane closures on I-20
  • SH 43 – At Kansas City Southern Railroad in Karnack, widening the bridge over the railroad. Northbound lanes closed with signal lights controlling one-way traffic.
  • US 80 – From Loop 390 to Interstate 20, resurfacing highway. Possible lane closures

 Marion County 

  • US 59 – From SH 49 to two miles north of SH 49, repairing and resurfacing highway. Lane closures, expect delays
  • US 59 – From Cass County line to 2 miles north of SH 49, installing safety barrier cable. Daily lane closures

 Morris County 

  • SH 49 – From Titus County line to FM 144, repairing and resurfacing highway. One-lane, two-way traffic

 Panola County 

  • US 59 (Loop) – From Business 59 North of Carthage to US 79 East, rehabilitating highway. Traffic detoured to ramps on eastbound/westbound Loop 59/79. Business 59 open to traffic
  • US 79 — From SH 149 to Rusk County line, rehabilitating highway
  • SH 149 – From US 79 to .8 miles south of SH 315, lane closures are possible during the final phase.

Titus County 

  • SH 49 – From FM 1735 to Morris County line, repairing and resurfacing highway. One-lane, two-way traffic
  • SH 49 – From Business 271 to Mount Pleasant city limits, repairing and resurfacing the road. One-lane, two-way traffic
  • US 271 – At Dickson Creek, Big Slough Creek, White Oak Creek & White Oak Creek Relief. Replacing bridges

 Upshur County 

  • US 271 – From 5.9 miles north of SH 155 to 1.5 miles north of SH 155, crews are resurfacing the highway.

TxDOT Paris District

Feb 27 – Mar 5, 2022

Delta, Lamar, Red River Counties

Contacts: Paris Area Office (903) 784-1357; Delta Co. Maintenance (903) 395-2139; Lamar Co. Maintenance (903) 785-4468; Red River Co. Maintenance (903) 427-3561.

SH 37, Red River County: from US 82 to Texas-Oklahoma state line, watch for temporary lane closures while crews resurface the roadway.

US 271, Red River County: from SH 37 to Titus County Line, watch for temporary lane closures while crews resurface the roadway.

FM 906, Lamar County: from FM 2648 to CR 47400. Watch for temporary lane closures while crews rehabilitate the existing pavement and improve drainage structures.

FM 38, Lamar County: from US 82 to US 82. Watch for temporary lane and shoulder closures while crews improve drainage structures and upgrade bridge rail and metal-beam guard fence.

FM 195, Red River County: from the Lamar County line to SH 37, watch for temporary lane and shoulder closures while crews improve drainage structures and replace bridge rail.

FM 1487, Red River County: from FM 909 to FM 910. Watch for temporary lane closures while crews widen and rehabilitate the existing pavement and improve drainage structures.

US 82, Red River County: from FM 1159 to the Bowie County line, watch for work zones and drive safely through construction areas as crews perform the final work.

Loop 286, Lamar County: FM 1497 around the North Loop to FM 1507. Watch for temporary lane and shoulder closures while crews improve guardrail and drainage structures.

Loop 286, Lamar County: from US 82 West around the North Loop to US 271 South interchange. Watch for temporary lane and shoulder closures while crews perform full-depth concrete repairs during overnight hours.

FM 64, Delta County: from FM 128 to SH 1532. Watch for temporary lane closures while crews rehabilitate the existing pavement and improve drainage structures.

Hopkins, Franklin Counties

Contacts: Sulphur Springs Area Office (903) 885-9514; Franklin Co. Maintenance (903) 537-4976; Hopkins Co. Maintenance (903) 885-4031.

SH 37, Franklin County: from the elementary school to US 67, watch for lane closures and short traffic delays as crews install the sidewalk.